Capacity: 127 MW
Cost: US$ 195.0 million
Operational Status: Planned
Companies Involved: Empresa Nacional de Electricidad (ENDE)
Investment Plans: Plan Óptimo de Expansión del Sistema Interconectado Nacional 2022, Bolivia
Exporting Options
More Information
Location:
Chapare, Cochabamba Department.
Timeline:
- Bidding: 2010.
- Technical, Economic, Social and Environmental Studies (TESA): 2010.
- Construction planned to start in 2011.
- Execution period: 2011-2014.
- Operation planned to start in 2014.